article Report Error Occurred During Processing

Related Documentation Version of up.time affected Affected Platforms
Adjusting the Java Heap Size All All

Symptom

When attempting to generate a report, the following error message appears in the report window or the Report Log section of the up.time user interface:

Report Error Occurred During Processing

Diagnosis and Resolution

There are several root causes that may contribute to this problem. Messages relating to the cause may appear in the uptime.log file. For assistance in diagnosing and resolving the issue, please generate and send a Problem Report to uptime Support.

To generate a Problem Report:

  • On the up.time tool bar, click Config.
  • In the Tree panel, click Problem Reporting.
  • If you do not want to include a copy the configuration data from your DataStore, click the Include config database dump option.
  • Click the Generate Report button.

Related Articles


Insufficient disk space to generate a report

RatingViews
article

This article explains how to deal with the up.time DATABASE! error.

By: uptime Support | Date Created: 1-25-2007 | Last Modified: 7-4-2011 | Index: 123

  3813

How do I generate a report?

RatingViews
article

Reports are useful when you need to pinpoint the source of a problem within you environment. With a report, you can visually analyze how individual critical resources - such as memory, CPU, and...

By: uptime Support | Date Created: 1-30-2009 | Last Modified: 8-25-2011 | Index: 351

  3107

Why did I receive duplicates of the same report?

RatingViews
article

There are a number of scenarios where this may happen 1) Has the report been saved twice? Check your 'My Portal' page for duplicate saves of the same report. 2) Are two or more instances of the...

By: uptime Support | Date Created: 12-31-1969 | Last Modified: 9-1-2011 | Index: 265

  2227

How do I stop a running report?

RatingViews
article

Reports that are currently running in the background, generally emailed reports or scheduled reports, cannot be manually stopped until they finish. If stopping the report is essential you must stop...

By: uptime Support | Date Created: 12-31-1969 | Last Modified: 8-10-2011 | Index: 266

  2183

How do I report LPAR capacity?

RatingViews
article

To create an LPAR Workload report, do the following: 1. In the Reports Tree panel, click LPAR Workload. 2. In the Date and Time Range area, select the dates and times on which to report. 3. Select...

By: uptime Support | Date Created: 12-31-1969 | Last Modified: 8-26-2011 | Index: 327

  3205

User Comments



No comments have been posted.

Copyright © 2021 IDERA, Inc.   Legal   Privacy Statement